Appropriateness
Typically, cost transfers are appropriate when they involve
allowable direct costs of the sponsored project and the
purpose is to:
- Correct errors in processing the original charge
- Move costs between projects for closely related work (as defined by the project scope) that is supported by more
than one funding source
- Transfer pre-award costs in accordance with the provisions
of OMB Circular A-110, Section C.25.e.1
Lack of Appropriateness
Inappropriate circumstances for cost transfers include,
but are not limited to, the following:
- When the transfer is largely for the purpose of utilizing
unexpended funds on a sponsored project
- When the transfer is for the purpose of avoiding or clearing
a cost overrun by charging another, unrelated sponsored
project
- When the transfer circumvents award terms and conditions
or the cost principles
Frequent, late, and inadequately explained or documented
transfers raise serious questions about the appropriateness
of the cost transfers and may result in audit disallowances.
Next...
|