The University of Wisconsin - Madison FEDERAL DEMONSTRATION PARTNERSHIP General Terms & Conditions And/or Agency Specific Requirements for Defense Agencies AFOSR, ONR, Army Med, Army (ARO), NASA
FDP
GENERAL TERMS AND CONDITIONS
OMB
Circulars referenced in the FDP Terms and Conditions
AGENCY SPECIFIC CONDITIONS:
FDP terms do not apply to Air Force Office of Scientific Research cooperative agreement contracts and other transactions.
|
AGENCY
|
TYPE OF EXPENDITURES/ACTION
|
REQUIREMENTS
|
HOW TO ACCOMPLISH
|
|
AFOSR
|
Pre-Award Costs (up to 90 days)
|
Requires University prior approval
|
Use
Form
88-1 "Request for Account Number in Advance
of Award"
|
|
|
No-Cost Time Extension
|
AFOSR must provide prior written approval
|
Letter to AFOSR Grant Officer at least 30 days prior to expiration date initiated by PI with signatures of PI and RSP
|
|
|
Carryover of Unobligated Funds
|
No prior approval necessary
|
Action initiated by RSP automatic carryover from one funding period to the next within a project period
|
|
|
Change in Scope or Objectives
|
AFOSR must give prior approval
|
Letter to AFOSR Grant Officer initiated by PI with signatures of PI and RSP
|
|
|
Absence or Change of PI
|
AFOSR must give prior approval
|
Letter to AFOSR Program Officer initiated by PI with signatures of PI, Chair and RSP
|
|
|
Relatedness of 2 or more projects
|
Awarding agency must give prior approval
|
Letter to the lead agency (majority funding) from PI requesting that two or more projects be determined to be related; signatures of PI and RSP
|
|
|
Foreign Travel
|
No prior approval necessary
|
See
foreign
air travel regulations
for federal projects
|
|
|
Subcontracting
|
No prior approval necessary as long as subcontractor is in original approved budget
|
UW subcontracting policies must be followed
|
|
|
Equipment
|
No prior approval necessary
|
Must
fit the definition of "equipment"
|
|
|
Rebudgeting
|
No prior approval necessary unless it changes the size or scope of the project
|
|
|
FDP terms do not apply to Office of Navy Research cooperative agreements, contracts and other transactions.
|
AGENCY
|
TYPE OF EXPENDITURES/ACTION
|
REQUIREMENTS
|
HOW TO ACCOMPLISH
|
|
ONR
|
Pre-Award Costs (up to 90 days)
|
Requires University prior approval
|
Use
Form
88-1 "Request for Account Number in Advance
of Award"
|
|
|
No-Cost Time Extension
|
ONR must provide prior written approval
|
Letter
from PI to ONR Administrative Grants Officer.
No cost extensions have specific
parameters for ONR
|
|
|
Carryover of Unobligated Funds
|
No prior approval necessary
|
Automatic carryover from one funding period to the next within a project period; action initiated by RSP
|
|
|
Change in Scope or Objectives
|
ONR must give prior approval
|
Letter to ONR Administrative Grants Officer initiated by PI with signatures of PI and RSP
|
|
|
Absence or Change of PI
|
ONR must give prior approval
|
Letter to ONR Administrative Grants Officer initiated by PI with signatures of PI, Chair and RSP
|
|
|
Relatedness of 2 or more projects
|
ONR must give prior approval
|
Letter to the lead agency (majority funding) from PI requesting that two or more projects be determined to be related; signatures of PI and RSP
|
|
|
Foreign Travel
|
No prior approval necessary
|
See
foreign
air travel regulations
for federal projects
|
|
|
Subcontracting
|
No prior approval necessary as long as subcontractor is in original approved budget
|
UW subcontracting policies must be followed
|
|
|
Equipment
|
No prior approval necessary
|
Must
fit the definition of "equipment"
|
|
|
Rebudgeting
|
No prior approval necessary unless it changes the size or scope of the project
|
|
|
U.S. Army Medical Research Acquisition Activity (USAMRAA) FDP terms cover research grants and cooperative agreements.
|
AGENCY
|
TYPE OF EXPENDITURES/ACTION
|
REQUIREMENTS
|
HOW TO ACCOMPLISH
|
|
Army
Med
|
Pre-Award Costs (up to 90 days)
|
Requires University prior approval
|
Use
Form
88-1 "Request for Account Number in Advance
of Award"
|
|
|
No-Cost Time Extension
|
No University approval required for 1st extension
|
Letter
from PI to RSP
accountant responsible
for account requesting extension
|
|
|
Carryover of Unobligated Funds
|
No prior approval necessary
|
Automatic carryover from one funding period to the next within a project period; action initiated by RSP
|
|
|
Change in Scope or Objectives
|
Army Med must give prior approval
|
Letter to Army Med Program Officer initiated by PI with signatures of PI and RSP
|
|
|
Absence or Change of PI
|
Army Med must give prior approval
|
Letter to Army Med Program Officer initiated by PI with signatures of PI, Chair and RSP
|
|
|
Relatedness of 2 or more projects
|
Army Med must give prior approval
|
Letter to the lead agency (majority funding) from PI requesting that two or more projects be determined to be related; signatures of PI and RSP
|
|
|
Foreign Travel
|
No prior approval necessary
|
See
foreign
air travel regulations
for federal projects
|
|
|
Subcontracting
|
No prior approval necessary as long as subcontractor is in original approved budget
|
UW subcontracting policies must be followed
|
|
|
Equipment
|
No prior approval necessary
|
Must
fit the definition of "equipment"
|
|
|
Rebudgeting
|
No prior approval necessary unless it changes the size or scope of the project
|
|
|
|
Human Subjects/Anatomical Substances
|
U.S. Army Surgeon General IRB must approve protocol and consent form before research begins
|
Specific requirements outlined in award
|
|
U.S. Army Research Office FDP conditions apply to all research grants, FDP conditions do not apply to cooperative agreements, other transactions and contracts.
|
AGENCY
|
TYPE OF EXPENDITURES/ACTION
|
REQUIREMENTS
|
HOW TO ACCOMPLISH
|
|
Army
(ARO)
|
Pre-Award Costs (up to 90 days)
|
Requires University prior approval
|
Use
Form
88-1 "Request for Account Number in Advance
of Award"
|
|
|
No-Cost Time Extension
|
ARO must give prior written approval
|
Letter from PI to ARO Grants Officer with supporting reasons and requested expiration date. Must be done at least 20 days prior to expiration of award
|
|
|
Carryover of Unobligated Funds
|
No prior approval necessary
|
Automatic carryover from one funding period to the next within a project period
|
|
|
Change in Scope or Objectives
|
ARO must give prior approval
|
Letter to ARO Grants Officer initiated by PI with signatures of PI and RSP
|
|
|
Absence or Change of PI
|
ARO must give prior approval
|
Letter to ARO Grants Officer initiated by PI with signatures of PI, Chair and RSP
|
|
|
Relatedness of 2 or more projects
|
ARO must give prior approval
|
Letter to the lead agency (majority funding) from PI requesting that two or more projects be determined to be related; signatures of PI and RSP
|
|
|
Foreign Travel
|
ARO must give prior approval if rebudgeted to include foreign travel occurs that was not specific in the awarded budget
|
Letter to ARO Grants Officer initiated by PI with signatures of PI and RSP
|
|
|
Subcontracting
|
No prior approval necessary unless it changes the size or scope of the project
|
UW subcontracting policies must be followed
|
|
|
Equipment
|
ARO must give prior approval if rebudgeted to include equipment over $5000 that was not specific in the awarded budget
|
Letter to ARO Grant Officer initiated by PI with signatures of PI and RSP
|
|
|
Rebudgeting
|
Prior approval necessary if rebudgeting includes foreign travel or equipment or changes size or scope of the project
|
Letter to ARO Grants Officer initiated by PI with signatures of PI and RSP
|
|
National Aeronautics and Space Administration FDP terms and conditions do not apply to contracts, cooperative agreements or other transactions with FDP members.
|
AGENCY
|
TYPE OF EXPENDITURES/ACTION
|
REQUIREMENTS
|
HOW TO ACCOMPLISH
|
|
NASA
|
Pre-Award Costs (up to 90 days)
|
Requires University prior approval
|
Use
Form
88-1 "Request for Account Number in Advance
of Award"
|
|
|
No-Cost Time Extension
|
No University approval required for 1st extension
|
Letter
from PI to RSP
accountant responsible
for account requesting extension
|
|
|
Carryover of Unobligated Funds
|
No prior approval necessary
|
Automatic carryover from one funding period to the next within a project period
|
|
|
Change in Scope or Objectives
|
NASA must give prior approval
|
Letter to NASA Grants Administrator initiated by PI with signatures of PI and RSP
|
|
|
Absence or Change of PI
|
NASA must give prior approval
|
Letter to NASA Grants Administrator initiated by PI with signatures of PI, Chair and RSP
|
|
|
Relatedness of 2 or more projects
|
NASA must give prior approval
|
Letter to the lead agency (majority funding) from PI requesting that two or more projects be determined to be related; signatures of PI and RSP
|
|
|
Foreign Travel
|
NASA prior written approval necessary
|
See
foreign
air travel regulations
for federal projects
|
|
|
Subcontracting
|
No prior approval necessary as long as subcontractor is in original approved budget
|
UW subcontracting policies must be followed
|
|
|
Equipment
|
No prior approval necessary
|
Must
fit the definition of "equipment"
|
|
|
Rebudgeting
|
No prior approval necessary unless it changes the size or scope of the project
|
|
|
|